Timeline

2002-2003 Prefeasiblity studies
January 2004 - August 2005 Detailed feasibility studies
February - April 2005 Enironmental Impact Statement released for public consultation
August 2005 Evaluation Report and Conditions of Development issued by Co-Ordinator General
December 2005 Tenders closed
January - April 2006 Tender evaluation
April 2006 RiverCity Motorway Group selected as preferred company to finance, build, own and operate  the tunnel
May 2006 RiverCity Motorway Group signed contract with Brisbane City Council
August 2006 Project achieved Financial Close
September 2006 Brisbane Lord Mayor turns first sod to mark the start of construction
October 2010 Project scheduled to be open to motorists

 